Photo: Leverington Avenue Parking Lot Plan

Leverington Avenue Parking Lot Plan

Project Description

The City of Philadelphia’s Department of Public Property will soon begin improvements to the Leverington Avenue Shopper’s Parking Lot. The contractor working for the Department of Public Property anticipates beginning construction activities at the lot on Monday, March 6, 2017 at 7:00 AM. The parking lot will be closed to vehicular access throughout certain points during the construction timeline.

Construction crews have begun work to renovate the lot including the repair of existing drainage channels, curbs, sidewalks and asphalt paving. Striping and landscaping as well as the installation of improved lighting will happen toward the end of the project.

Project Updates

The Department of Public Property has recently announced upcoming closures for the Leverington Avenue Parking Lot to complete improvements to the lot. As a courtesy to local business owners and residents the Roxborough Development Corporation has prepared this notice to provide an update on the tentative construction dates and anticipated closures.

Tentative dates for Leverington Avenue Parking Lot closures for the seal coating and striping of the parking lot:

Monday, September 25, 2017 to Tuesday, September 26, 2017
Preparation and seal coat application. PARKING LOT CLOSED TO ALL VEHICULAR TRAFFIC, TRASH ACCESS & DELIVERIES

Wednesday, September 27, 2017
Possible carry over work day for seal coating, pending on time required for adequate curing. PARKING LOT CLOSED TO ALL VEHICULAR TRAFFIC, TRASH ACCESS & DELIVERIES

Thursday, September 28, 2017
Parking lot line striping. PARKING LOT CLOSED TO ALL VEHICULAR TRAFFIC, TRASH ACCESS & DELIVERIES

The lot will need to be closed to the public, employee's, delivery services, trash pick-up, etc. until all work is completed.

DUMPSTERS, Trash containers, grease barrels etc. TO BE located AND REMAIN in the NEW ENCLOSURE BUILT. All the above is based on weather permitting.

Parking Lot Management

Following completion of the renovations, the Roxborough Development Corporation will assume responsibilities to manage the lot to ensure it is properly maintained and plowed in the winter months. Parking passes will be made available for residents parking in the lot over the 2-hour time limit.